Urangan Harbour MSQ Base of Operations Pontoon
CLIENT: Marine Safety Queensland & The Department of Transport and Main roads
DATE OF COMPLETION: December 2018
EQUIPMENT:
WORK SCOPE:
-
Dredging of the site by barge and excavator with the spoil trucked and disposed of off-site;
-
Remediation and repair work to the existing southern pontoon;
-
Supply of a marine Palfinger Crane for the installation by MSQ at a later date;
-
Demolition and removal of existing northern pontoon and piles;
-
Design, supply, and installation of a 12 x 3.0m TMR spec pontoon;
-
Installation of 2 x 457 Dia steel piles into sandstone;